Step-by-Step Timeline for Built-in Carpentry in HDB BTO Renovations (2025 Edition)

Renovation delays are one of the biggest headaches for new BTO owners. While hacking and tiling are straightforward, carpentry is often where schedules slip. Why? Because carpentry involves:

  1. Precise on-site measurements
  2. Off-site factory fabrication
  3. Delivery logistics
  4. On-site installation and finishing

If you know the realistic carpentry timeline, you can plan better for key collection, furniture delivery, and your actual move-in date.

At HDBGROUPRENO.SG PTE. LTD, we coordinate carpentry works in group batches, ensuring faster production and fewer delays compared to one-off projects.


1. Pre-Fabrication Stage (Week 1)

  • Site Measurement: After keys are collected, our team measures every inch of your flat.
  • Design Finalisation: Confirm wardrobe dimensions, kitchen layout, TV console specs.
  • Material Selection: Choose laminates, quartz tops, handles, hinges.
  • HDB Approval (if required): Certain built-ins near service ducts or electrical risers may need clearance.

⏳ Timeline: 1–2 weeks


2. Factory Production Stage (Week 2–3)

  • Cutting & Assembly: Boards cut to size with CNC precision.
  • Lamination: Surfaces finished with chosen laminate or acrylic.
  • Quality Check: Alignment, finishing, and hardware prep.

⏳ Timeline: 2–3 weeks
📦 Group Reno Advantage: Shared factory production for multiple BTO flats reduces waiting time and material wastage.


3. Delivery & Site Preparation (Week 4)

  • Floor & wall protection installed before delivery.
  • Carpentry delivered in modular sections (wardrobes, cabinets, shelving).
  • Electrical points double-checked before cabinet installation.

⏳ Timeline: 1 week


4. On-Site Installation (Week 5–6)

  • Kitchen Cabinets: Installed first, followed by countertop fitting.
  • Wardrobes & Storage: Master bedroom, common rooms.
  • TV Console & Feature Wall: Including hidden wiring.
  • Study Desk & Shoe Cabinet: Final secondary units.

⏳ Timeline: 2 weeks


5. Finishing & Handover (Week 7)

  • Touch-Ups: Alignment checks, sealing edges, caulking joints.
  • Appliance Integration: Hob, hood, oven, washing machine fitted.
  • Defect Rectification: Minor adjustments, polish, clean-up.
  • Final Handover: Walk-through with homeowner, warranty issued.

⏳ Timeline: 1–2 weeks


6. Common Causes of Carpentry Delays

  • Late design confirmation → factory cannot start production
  • Imported laminates out of stock → 1–2 weeks delay
  • Rainy season humidity → slower curing of adhesives
  • Poor coordination between carpentry & electrical teams

💡 Tip: Confirm designs & finishes before key collection to cut 2–3 weeks off your timeline.


7. Case Study – 4-Room Tengah BTO Carpentry Timeline

  • Week 1: Measurements & design finalised
  • Week 3–4: Kitchen + wardrobe fabrication
  • Week 6: Delivery & prep
  • Week 7–8: On-site installation complete
  • Week 9: Final touch-up
    ✅ Total timeline: 9 weeks (2 weeks faster due to Group Reno batch production)

FAQ (Optimised for Snippets)

Q1: How long does BTO carpentry take in Singapore?
👉 Around 6–10 weeks, depending on scope and factory slots.

Q2: Which carpentry items take the longest?
👉 Kitchen cabinets, because of countertop fitting and appliance integration.

Q3: Can carpentry be done before tiling?
👉 No. Flooring, tiling and painting must be finished before installation.

Q4: How to shorten the carpentry timeline?
👉 Confirm designs early, join a Group Reno package, choose in-stock laminates.


Why Choose HDBGROUPRENO.SG PTE. LTD

  • 🛠️ Precise timeline control with milestone updates
  • 🏡 Group carpentry batches to cut waiting time
  • 🎨 Custom wardrobes, kitchens, study desks designed for your layout
  • 💰 Save 10–20% compared to standalone projects
  • 🖥️ Free 3D virtual tours to visualise before fabrication

Want your BTO carpentry delivered on time and within budget?
👉 Book a Free 3D Virtual Tour + Quotation
👉 Explore Active Group Carpentry Projects

Leave a Reply

Your email address will not be published. Required fields are marked *

6 + 3 = ?