Renovation delays are one of the biggest headaches for new BTO owners. While hacking and tiling are straightforward, carpentry is often where schedules slip. Why? Because carpentry involves:
- Precise on-site measurements
- Off-site factory fabrication
- Delivery logistics
- On-site installation and finishing
If you know the realistic carpentry timeline, you can plan better for key collection, furniture delivery, and your actual move-in date.
At HDBGROUPRENO.SG PTE. LTD, we coordinate carpentry works in group batches, ensuring faster production and fewer delays compared to one-off projects.
1. Pre-Fabrication Stage (Week 1)
- Site Measurement: After keys are collected, our team measures every inch of your flat.
- Design Finalisation: Confirm wardrobe dimensions, kitchen layout, TV console specs.
- Material Selection: Choose laminates, quartz tops, handles, hinges.
- HDB Approval (if required): Certain built-ins near service ducts or electrical risers may need clearance.
⏳ Timeline: 1–2 weeks
2. Factory Production Stage (Week 2–3)
- Cutting & Assembly: Boards cut to size with CNC precision.
- Lamination: Surfaces finished with chosen laminate or acrylic.
- Quality Check: Alignment, finishing, and hardware prep.
⏳ Timeline: 2–3 weeks
📦 Group Reno Advantage: Shared factory production for multiple BTO flats reduces waiting time and material wastage.
3. Delivery & Site Preparation (Week 4)
- Floor & wall protection installed before delivery.
- Carpentry delivered in modular sections (wardrobes, cabinets, shelving).
- Electrical points double-checked before cabinet installation.
⏳ Timeline: 1 week
4. On-Site Installation (Week 5–6)
- Kitchen Cabinets: Installed first, followed by countertop fitting.
- Wardrobes & Storage: Master bedroom, common rooms.
- TV Console & Feature Wall: Including hidden wiring.
- Study Desk & Shoe Cabinet: Final secondary units.
⏳ Timeline: 2 weeks
5. Finishing & Handover (Week 7)
- Touch-Ups: Alignment checks, sealing edges, caulking joints.
- Appliance Integration: Hob, hood, oven, washing machine fitted.
- Defect Rectification: Minor adjustments, polish, clean-up.
- Final Handover: Walk-through with homeowner, warranty issued.
⏳ Timeline: 1–2 weeks
6. Common Causes of Carpentry Delays
- Late design confirmation → factory cannot start production
- Imported laminates out of stock → 1–2 weeks delay
- Rainy season humidity → slower curing of adhesives
- Poor coordination between carpentry & electrical teams
💡 Tip: Confirm designs & finishes before key collection to cut 2–3 weeks off your timeline.
7. Case Study – 4-Room Tengah BTO Carpentry Timeline
- Week 1: Measurements & design finalised
- Week 3–4: Kitchen + wardrobe fabrication
- Week 6: Delivery & prep
- Week 7–8: On-site installation complete
- Week 9: Final touch-up
✅ Total timeline: 9 weeks (2 weeks faster due to Group Reno batch production)
FAQ (Optimised for Snippets)
Q1: How long does BTO carpentry take in Singapore?
👉 Around 6–10 weeks, depending on scope and factory slots.
Q2: Which carpentry items take the longest?
👉 Kitchen cabinets, because of countertop fitting and appliance integration.
Q3: Can carpentry be done before tiling?
👉 No. Flooring, tiling and painting must be finished before installation.
Q4: How to shorten the carpentry timeline?
👉 Confirm designs early, join a Group Reno package, choose in-stock laminates.
Why Choose HDBGROUPRENO.SG PTE. LTD
- 🛠️ Precise timeline control with milestone updates
- 🏡 Group carpentry batches to cut waiting time
- 🎨 Custom wardrobes, kitchens, study desks designed for your layout
- 💰 Save 10–20% compared to standalone projects
- 🖥️ Free 3D virtual tours to visualise before fabrication
Want your BTO carpentry delivered on time and within budget?
👉 Book a Free 3D Virtual Tour + Quotation
👉 Explore Active Group Carpentry Projects